Prepare a scope decision a sponsor can sign

Give a sponsor meaningful options when a requested addition threatens a committed date.

Illustrative case

The situation

A sponsor requests an extra reporting module two weeks before rollout. The delivery lead estimates three extra days of configuration plus one day for acceptance. The only available tester is already booked for launch rehearsal.

Work through the evidence

Document the request, acceptance criteria and the constraint. Prepare three options: defer the module, swap it for existing scope with sponsor agreement, or change the date. Include dependencies and uncertainty for each. Name who can authorize the baseline change.

Make the decision

Recommend deferral if the existing launch date has priority and no scope can move. If the reporting module is mandatory at launch, reopen the tradeoff with the sponsor. Record the chosen option and notify the owners of the affected commitments.